Electrical connection

#
Documentation to be submitted
Document
1.
Submit a request for connection to the electricity network (original)
Download WORD
2.
Identity card in the case of a natural person or a decision on the registration of a company in the case of a legal entity
3.
When it is the case that the facility under construction is connected to the electricity network, then the following are submitted:
Urban technical conditions (2 originals)
Revised main project (original)
4.
Signing a contract for connection to the electricity network