Electrical connection
# | Documentation to be submitted | Document | |
---|---|---|---|
1. | Submit a request for connection to the electricity network (original) | Download WORD | |
2. | Identity card in the case of a natural person or a decision on the registration of a company in the case of a legal entity | ||
3. | When it is the case that the facility under construction is connected to the electricity network, then the following are submitted: | ||
Urban technical conditions (2 originals) | |||
Revised main project (original) | |||
4. | Signing a contract for connection to the electricity network |